UPDATED: Summer 2025 Road Maintenance Schedule
UPDATED 8/12/25: All resurfacing work has been completed on schedule. Thank you for your patience and cooperation.
Chatham Township will be paving roads in the near future. Below is a tentative schedule for milling and paving. These dates are subject to change due to weather or other unforeseen construction issues. The schedule below will be updated continuously with any changes until all scheduled projects are completed.
Street Name | Milling Approx. Date | Paving Approx. Date |
Dellwood Avenue | August 6, 2025: COMPLETED | August 12, 2025: COMPLETED |
Overlook Road | August 6, 2025: COMPLETED | August 11, 2025: COMPLETED |
Old Farm Road | August 7, 2025: COMPLETED | August 11, 2025: COMPLETED |
Britten Road | August 7, 2025: COMPLETED | August 12, 2025: COMPLETED |
All vehicles must be removed from the road on days of milling and paving. You will have access to your driveway during road milling, though temporary delays will occur when the road is being milled in front of your property. If you need to use your vehicle on paving dates, you will have to move your vehicle to another location prior to 7AM and walk to your car. Please note the newly paved road cannot be driven on until cones have been removed from the end of the road by authorized personnel.
If you have any questions regarding this project, please do not hesitate to contact Erica Vigliorolo at 973-921-2298 or John Ruschke at 908-238-5000.
Thank you for your patience and cooperation as we continue to improve our town’s infrastructure!